“GANINANG hapon, atong gipahigayon ang Turnover Ceremony sa Covered Court sa Kauswagan National High School ug sa Interment Building sa Kabina,” Cagayan de Oro City first district Rep. Lordan Suan reported.
“Kini nga mga proyekto bunga sa atong paningkamot nga mapalambu ang mga pasilidad ug serbisyo sa distrito. Daghang salamat sa tanan nga nitambong ug misuporta—padayon ta sa tinuod nga serbisyo,” he added.
PROJECT DESCRIPTION: Construction of 30m by 21m covered court with cadding, 60m lined canal and basketball rings.
CONTRACT DESCRIPTION:
Implementing Office : DPWH-X, CDO 1* DEO
Project Engineer :Grace D. Julian
Station Limit
Source of Fund :FY 2024 GAA
Appropriation :Php 15,000,000.00
Contractor : RBT Ventures
Original Contract Amount : P14404,500.00
Revised Contract Amount :P14,850,000.00
: 180 Days
Original Contract Time Calendar
Calendar
Revised Contract Time :258 Days
Contract Effectivity : March 26, 2024
PROJECT DESCRIPTION: Construction of Two (2) Stony Multi-Purpose (Internment) building with two (2) main rooms, with one pantry, one (1) rest room, one (2) EE/ME room, one (1) utility room, a balcony and a porch.
CONTRACT DESCRIPTION:
Implementing Office : DPWH-X, CDO 1 DEO
Project Engineer : Grace D. Julian
Station Lumit :FY 2024 GAA
Source of Fund : Php 15,000,000.00
Appropriation : RBT Ventures
Contractor :P14,404,500.00
Orlginal Contract Amount :P14,850,000.00
Revised Contract Amount : 180 Calendar Davs
Orlginal Contract Time :258 Calendar Days
Revised Contract Time :March 26, 2024
Contract Effectivity